title: Decision Log
|
|
slug: /decisions/
|
|
sidebar_position: 2
|
|
---
|
|
|
|
# Decision Log
|
|
|
|
| Date | Decision | Scope | Owner | Record |
|
|
|---|---|---|---|---|
|
|
| 2026-08-20 | Add Jenny to the Corp v1 Board and every active project | Corp v1 governance, AeroSim, and Maze Next Gen | RootAtSkic | [Jenny Board and project membership](/governance/decisions/jenny-board-and-project-membership/) |
|
|
| 2026-08-17 | Authorize Maze Next Gen kickoff and begin provisioning | Maze Next Gen | RootAtSkic | [Maze Next Gen kickoff](/governance/decisions/mazeng-kickoff/) |
|
|
| 2026-08-17 | Add Linas to the Corp v1 Board and AeroSim team | Corp v1 governance and AeroSim | RootAtSkic | [Linas Board and AeroSim membership](/governance/decisions/linas-board-and-aerosim-membership/) |
|
|
| 2026-08-14 | Add Eduard to the Corp v1 Board and expand the AeroSim team | Corp v1 governance and AeroSim | RootAtSkic | [Board and AeroSim membership expansion](/governance/decisions/board-and-aerosim-membership-expansion/) |
|
|
| 2026-08-14 | Establish the Corp v1 Board, main skill, portal, membership, and skill-change authority | Corp v1 governance | RootAtSkic | [Corp v1 Board migration](/governance/decisions/corp-v1-board-migration/) |
|
|
| 2026-08-13 | Align managed projects to the six-channel Scope/Kanban lifecycle and hourly synchronization model | Corp v1 managed projects | RootAtSkic | [Managed-project six-channel alignment](/governance/decisions/managed-project-six-channel-alignment/) |
|
|
| 2026-08-12 | Authorize AeroSim test kickoff and begin provisioning | AeroSim | RootAtSkic | [AeroSim kickoff](/governance/decisions/aerosim-kickoff/) |
|
|
|
|
Every kickoff, pause, restart, material scope change, and shutdown requires a dated decision record with context, decision, rationale, accountable owner, and consequences.
|